| High risk condition |
Why this is high risk |
 |
The project periods don't match. |
The original transaction date occurred outside the project period of the fund receiving the cost.
|
 |
The transaction date is too old. |
- The transfer is to or from an NIH award and the original transaction date occurred three or more months ago.
- The transfer is to or from a non-NIH federal award and the original transaction date occurred four or more months ago.
|
 |
A terminating award is involved. |
The transferred cost is to a federal fund within the last 30 days of the originating award.
|
 |
The cost was previously moved. |
The cost is being transferred to a federal fund and was previously moved as an expense transfer.
|
 |
A fund is in an overdraft condition. |
- The cost is being transferred to a sponsored fund that is in an overdraft condition (includes federal flow-through funds).
- The cost is being transferred from any fund in an overdraft condition to a federal fund.
|
 |
The transfer includes an account code designated as "E."
|
The expense transfer has an unallowable account code (E or error code) for a federal fund.
|